How Much Will Rwanda’s F1 Track Cost?

15 October 202611 min read
Updated 2 days ago

Rwanda hasn’t said what its new F1 circuit at Bugesera will cost, and neither has Formula 1. Reported figures run from about $150m to $1.2bn. Here’s where each one comes from, how they compare with what tracks like the Circuit of the Americas cost and what Rwanda could pay F1 each year to host the race.

Dan Sweeting

UK-based owner and editor of F1 Salaries. I track what F1 drivers, teams, staff and sponsors earn.

Summarize this article inClaudeChatGPTGeminiPerplexityGrok

Key Takeaways

Rwanda and F1 haven’t published a build cost for the Bugesera circuit or the hosting fee

Reported estimates range from about $150m to $1.2bn, and the top figure is the least reliable

Recent purpose-built F1 tracks have cost $150m-400m, led by the Circuit of the Americas

A hosting fee at Qatar’s level of about $55m a year would add up to $550m over the 10-year deal

The first race depends on the $2bn Bugesera airport next door, which is due in early 2028

The Three Reported Cost Estimates

No official figure has been published. Formula 1’s announcement on October 13, 2026, covered the 10-year deal, the Bugesera site and the FIA Grade 1 standard the circuit will be built to, but it didn’t include a construction cost or the fee Rwanda will pay to host the race. The Rwanda Development Board, which is leading the project, hasn’t given one either.

Three figures have been reported, and they’re far apart.

  • $150m. Mentioned in an analysis of the deal by Uchumi360, which flags it as unconfirmed.
  • $270m. Kenya’s Daily Nation gave this as an industry estimate for building any Grade 1 F1 circuit, plus around $18.5m a year in upkeep. It’s a general benchmark for Grade 1 circuits, and Pulse Kenya has since used it as the opening estimate for Bugesera.
  • $1.2bn. The Borgen Project described a $1.2bn circuit near the airport in June 2026, and Pulse Kenya put the top end at $1.22bn. GPblog gives the same $1.2bn for Morocco’s rival motorsport and tourism complex near Tangier, so treat this one with caution.

Our read is that the track itself, with its pit building, paddock and grandstands, will land somewhere in the $200m-400m range. That’s what comparable permanent circuits have cost, as the table below shows, and IOL puts a modern circuit at anywhere between $200m and more than $1bn. Alex Wurz says the layout follows the existing hills and the lake, which should limit the earthworks on a site that has nothing built on it yet.

Sources

What Is Rwanda Building at Bugesera?

Carsten Tilke and Alex Wurz in Kigali

Carsten Tilke and Alex Wurz at the Kigali Announcement. Credit: formula1.com

The circuit will sit about 40km south of Kigali, next to the new Bugesera International Airport. It’s planned at about 6km with 17 corners, runs anti-clockwise and gains 197m in elevation over a lap, which Wurz compared to a roller coaster. His company WurzDesign drew the layout, and Tilke Engineers and Architects and the consultancy DAR are working with it on the engineering.

Carsten Tilke said the track will run between two hills that act as a natural grandstand, with a straight of more than 1km and fast corners beside a lake. The venue is planned for about 100,000 fans and will be built to FIA Grade 1, the standard every F1 circuit needs.

Formula 1 says the site will also host other motorsport, concerts, conferences and events through the year. That matters for the cost, because a circuit that only opens for one race weekend is hard to pay for.

Sources

More Articles

Read more on the money behind Formula 1

What Other New F1 Tracks Cost

Our F1 track guides record what each circuit on the calendar cost to build. These are the purpose-built and semi-permanent venues that make the closest comparison with Bugesera. The figures are what each one cost when it was built, so the older ones would cost more today.

CircuitOpenedBuild CostFigure From
Circuit of the Americas2012Around $400mFIA
Shanghai International Circuit2004$240mAFP
Madring2026£125m ($166m)Formula1.com
Istanbul Park2005$150m+Grandprix.com
Lusail International Circuit2004Around $58mBrembo

The Circuit of the Americas is the closest match. Like Bugesera, it was built from scratch on open land with a big main grandstand, an observation tower and a plaza, and it came in at about $400m in 2012 against an early estimate of $250m.

Lusail shows how the bill can grow later. It cost about $58m in 2004 as a MotoGP track, then Qatar’s Public Works Authority rebuilt the facilities before F1’s 10-year deal began in 2023, with one contract alone reported at $185m. Yas Marina in Abu Dhabi was billed as the most expensive circuit ever built, but it came with a hotel and a marina, so there’s no price for the track alone. Rwanda’s project is similar, with homes and hotels planned around the circuit.

Las Vegas is the outlier. Liberty Media paid $240m for the land for its pit and paddock building and put the building and track work at close to $400m, on top of an $80m repaving job on public roads.

Sources

How Much Will Rwanda Pay F1 to Host the Race?

Stefano Domenicali at the Kigali announcement

Stefano Domenicali at the Kigali Announcement on October 13. Credit: formula1.com

That hasn’t been published either, and over the life of the deal it’s likely to cost more than the track. Race promoters pay Formula 1 a fee every year, and Pulse Kenya puts the usual range at $20m-60m. Qatar and Saudi Arabia are reported to pay about $55m a year, and Speedcafe estimated Madrid’s new race at $50m.

If Rwanda pays something close to Qatar, the 10-year deal would come to about $550m in hosting fees alone. A fee of $55m a year is more than any driver on our F1 driver salaries list earns apart from Max Verstappen and Lewis Hamilton. IOL worked out that a fee at that level would equal about 0.4% of Rwanda’s economy, which is worth roughly $15bn, and about 8.5% of the $647m the country earned from tourism in 2024.

Visit Rwanda, the Rwanda Development Board’s tourism brand, is the race’s title partner. It’s the same brand Rwanda already pays to put on the sleeves of Arsenal, Paris Saint-Germain and Bayern Munich shirts. South Africa’s sports minister Gayton McKenzie put the yearly cost of staging a race in his country at about 2bn rand ($106m), which covers running the event as well as the fee.

Sources

Ticket Prices

Compare ticket prices for every race on the 2026 calendar

Why the Race Date Depends on the Airport

The first race won’t get a date until the airport next door is open. Jean-Guy Afrika, chief executive of the Rwanda Development Board, said Bugesera International Airport is due to be finished in early 2028, which is why the first African Grand Prix is expected in 2030 or 2031. F1’s own statement only commits to early in the next decade.

The airport is the bigger project. Its cost has risen to about $2bn from an earlier $1.3bn, and IOL notes that the IMF has warned it’ll add to Rwanda’s debt pressures. The Qatar Investment Authority completed the purchase of a 60% stake from Qatar Airways for $578m on June 1, 2026, and committed another $1.1bn to finish it, according to GPblog. Rwanda’s Aviation Travel and Logistics holding company owns the other 40%. Qatar Airways is also Formula 1’s global airline partner.

Sources

Will the African Grand Prix Pay Off for Rwanda?

The 1993 South African Grand Prix at Kyalami

Kyalami in South Africa Where F1 Last Raced in Africa in 1993. Credit: formula1.com

Formula 1 says its races typically bring more than £100m a year to a host country’s economy, though that’s the sport’s own projection. IOL argues the big impact figures from Las Vegas and Miami come from rich visitor markets and don’t carry over neatly to Rwanda, where gross national income is about $1,040 a person.

Rwanda’s case rests on tourism and on a venue that’s busy all year. F1 says Africa has more than 100 million F1 fans, and the Rwanda Development Board plans homes and hotels around the circuit as part of a new district by the airport. It would be F1’s first race in Africa since the 1993 South African Grand Prix at Kyalami.

Ticket prices are another hurdle for local fans. Rwanda’s income per head works out at about $87 a month, and a three-day pass costs more than that at most races on our F1 ticket prices list.

The deal has drawn criticism too. Amnesty International UK called it sportswashing, and in early 2025 the foreign minister of the Democratic Republic of Congo wrote to F1 urging it to rule Rwanda out over its alleged support for M23 rebels, which Rwanda denies.

Sources

Frequently Asked Questions

How much will the Rwanda F1 track cost?

No official cost has been published for Rwanda’s F1 track at Bugesera. Reported figures run from about $150m to $1.2bn, and $270m is the most quoted estimate for a Grade 1 circuit. Recent purpose-built F1 tracks have cost $150m-400m, with the Circuit of the Americas at around $400m in 2012.

When is Rwanda hosting F1?

Rwanda will host the African Grand Prix from the early 2030s under a 10-year deal announced on October 13, 2026. No date has been set yet. The race needs the new circuit at Bugesera and the airport next to it, which is due in early 2028, so 2030 or 2031 is the most likely start.

Who designed the Rwanda F1 track?

Former F1 driver Alex Wurz designed the Rwanda F1 track through his company WurzDesign. Tilke Engineers and Architects, run by Carsten Tilke, and the consultancy DAR are working with him on the engineering. The roughly 6km layout has 17 corners, runs anti-clockwise and climbs 197m over a lap between two hills and a lake.

Where is the Rwanda F1 track?

The Rwanda F1 track will be built in Bugesera, about 40km (25 miles) south of the capital Kigali. It sits next to the new Bugesera International Airport as part of a wider sports, tourism and business development led by the Rwanda Development Board. Construction of the circuit itself hasn’t started yet.

Why is it called the African Grand Prix?

Rwanda chose the name African Grand Prix because it wants the race to stand for the whole continent. Jean-Guy Afrika of the Rwanda Development Board said calling it the Kigali or Rwanda Grand Prix would have felt exclusive, and the wider name makes it easier to bring in partners. It’s F1’s first race in Africa since 1993.

Sources
F1 SALARIES INSIDER

Get the Money Side of F1 Every Thursday

Get stories like this in one free email every Thursday, with the last race by salary, the next race, a featured driver, and the latest driver market moves.
Want every issue in full? Get Insider+ for $5 a month or $40 a year.

Insider · Issue 23

01 · The Last Race

Singapore by Salary

Pos

Driver

Pts

Salary

1

Max Verstappen

Red Bull

25

$70m

2

Charles Leclerc

Ferrari

18

$34m

3

Kimi Antonelli

Mercedes

15

$3.4m

4

Lando Norris

McLaren

12

$30m

5

Oscar Piastri

McLaren

10

$13m

6

Insider+

7

Insider+

Our Take · Insider+

What Each Point Now Costs Red Bull

Shining a light on the finances that make Formula 1 drive, from drivers, teams, staff, and sponsors to tracks, tickets, and much more.
Figures are estimates unless labeled Verified. Sources and review dates sit with the figures they support.
F1 Salaries is independent, isn't affiliated with Formula 1 or any team, and accepts no affiliate or paid content.

F1 Salaries Insider

The week's F1 money news in one free email every Thursday.

We never sell, rent, or share your email address.